title: "Routing for one or several teams"
output:
  rmarkdown::html_vignette:
    css: fieldopt.css
vignette: >
  %\VignetteIndexEntry{Routing for one or several teams}
  %\VignetteEngine{knitr::rmarkdown}
  %\VignetteEncoding{UTF-8}
---

<!-- Generated from routing-teams.Rmd.orig by tools/precompute-vignettes.R; edit the .orig file. -->



The same sample can be worked by one team on a long tour or by several teams
on short routes. The total travel differs, the number of days differs and the
cost differs. This vignette compares those organisations on one sample.


``` r
library(fieldopt)
library(dplyr, warn.conflicts = FALSE)
set.seed(7)
frame <- tibble(
  unit = c("depot", paste0("s", 1:60)),
  lat = c(-8.05, -8.05 + runif(60, -0.25, 0.25)),
  lon = c(-35.00, -35.00 + runif(60, -0.35, 0.35))
)
m <- travel_matrix(frame)
model <- field_cost_model(
  per_travel = 1.8, per_unit = 40, per_interview = 12,
  interviews_per_unit = 6, currency = "BRL"
)
s <- frame |>
  filter(unit != "depot") |>
  select_units(n = 18, seed = 3)
```

## One tour


``` r
one <- route_fieldwork(m, units = s, depot = "depot", cost_model = model)
one
#> 
#> ── Field routes ────────────────────────────────────────────────────────────────
#> 1 route from "depot" through 18 units: total travel 260.6 km (proven optimal).
#> Route 1 (260.6): s10 > s30 > s44 > s52 > s38 > s25 > s23 > s27 > s40 > s34 >
#> s18 > s58 > s47 > s22 > s28 > s21 > s39 > s6
#> Cost (BRL): travel 469.1 + routes 0 + units 720 + interviews 1296 = 2485.
```

## Routes limited by length

A team that must return to the depot every day has a maximum route length,
here 100 km. The solver splits the tour optimally under that limit (Prins
2004) and improves each route locally.


``` r
days <- route_fieldwork(
  m,
  units = s, depot = "depot", max_length = 100,
  cost_model = model
)
days
#> 
#> ── Field routes ────────────────────────────────────────────────────────────────
#> 4 routes from "depot" through 18 units: total travel 354.8 km (lower bound
#> 189.8, gap 87%).
#> Route 1 (97.7): s27 > s23 > s25 > s38 > s52
#> Route 2 (91.75): s30 > s18 > s34 > s40 > s44 > s10
#> Route 3 (78.45): s6 > s39 > s21 > s28
#> Route 4 (86.94): s58 > s47 > s22
#> Cost (BRL): travel 638.7 + routes 0 + units 720 + interviews 1296 = 2655.
autoplot(days)
```

![Figure of the chunk days](figures/routing-teams-days-1.png)

## Routes limited by stops

A team that can interview at most four units a day has a stop limit instead.


``` r
stops <- route_fieldwork(
  m,
  units = s, depot = "depot", max_stops = 4,
  cost_model = model
)
stops
#> 
#> ── Field routes ────────────────────────────────────────────────────────────────
#> 5 routes from "depot" through 18 units: total travel 372 km (lower bound 189.8,
#> gap 96%).
#> Route 1 (108.7): s18 > s34 > s40 > s27
#> Route 2 (73.8): s52 > s38 > s23 > s25
#> Route 3 (78.45): s28 > s21 > s39 > s6
#> Route 4 (86.94): s58 > s47 > s22
#> Route 5 (24.12): s30 > s44 > s10
#> Cost (BRL): travel 669.5 + routes 0 + units 720 + interviews 1296 = 2686.
```

## Comparing


``` r
bind_rows(
  `one tour` = glance(one),
  `100 km per route` = glance(days),
  `4 stops per route` = glance(stops),
  .id = "organisation"
) |>
  select(organisation, n_routes, travel_km = total, cost) |>
  mutate(across(c(travel_km, cost), round))
#> # A tibble: 3 × 4
#>   organisation      n_routes travel_km  cost
#>   <chr>                <int>     <dbl> <dbl>
#> 1 one tour                 1       261  2485
#> 2 100 km per route         4       355  2655
#> 3 4 stops per route        5       372  2686
```

The travel grows with the number of routes because every route starts and
ends at the depot; the question for the planner is whether the extra kilometres
are cheaper than the extra days or teams, which is a cost model question, not
a routing one.

## Road distances

Distances from coordinates understate travel on real roads. Two ways to do
better, both feeding the same routing and cost functions:

* a **detour factor**, the ratio of road to straight-line distance, which on
  rural networks usually lies between 1.2 and 1.4: a planning estimate when
  no network is at hand;
* a **road-network matrix** from an OSRM server, with `method = "osrm"`:
  durations in minutes or distances in kilometres, requested in blocks so
  that the server's table limit is respected. The public demo server is for
  small tests; run your own server (with OpenStreetMap data of the region)
  for a frame. A matrix computed by any other engine can be passed through
  `matrix` instead.


``` r
m_detour <- travel_matrix(frame, detour = 1.3)
m_detour
#> Travel matrix: 61 units, haversine x 1.3 (km); mean off-diagonal 42.48.
```


``` r
m_road <- travel_matrix(frame, method = "osrm", measure = "duration")
route_fieldwork(m_road, units = s, depot = "depot", max_length = 480) # 8 hours per route
```

The `snap` attribute of an OSRM matrix gives the distance from each unit to
the nearest point of the network the server could use; units snapped from
far away are the ones whose access the field team should check.

## Time at the unit, cost per team-day and the calendar

When the matrix is in minutes, a day has a length and so does the work at
each unit: `service_time` is added to the travel of a route when the limit
is checked (a segment with nine points and a few interviews can take two
hours), and the cost model's `per_route` charges each route as a team-day
(allowances, vehicle, lodging). Routes are then days of work.


``` r
daily <- field_cost_model(
  per_travel = 0.5, per_route = 400, per_unit = 20, per_interview = 15,
  interviews_per_unit = 3, currency = "BRL"
)
day <- frame |>
  travel_matrix(detour = 1.3, speed = 60) |> # kilometres at 60 km/h: minutes
  route_fieldwork(
    units = s, depot = "depot", max_length = 480, service_time = 120,
    iterations = 50, cost_model = daily
  )
day
#> 
#> ── Field routes ────────────────────────────────────────────────────────────────
#> 6 routes from "depot" through 18 units: total travel 571.4 min (lower bound
#> 246.7, gap 132%).
#> Route 1 (31.35, duration 391.4): s10 > s44 > s30
#> Route 2 (113, duration 473): s58 > s47 > s22
#> Route 3 (99.32, duration 459.3): s39 > s21 > s28
#> Route 4 (116, duration 476): s6 > s25 > s23
#> Route 5 (115.9, duration 475.9): s40 > s34 > s18
#> Route 6 (95.81, duration 455.8): s52 > s38 > s27
#> Cost (BRL): travel 285.7 + routes 2400 + units 360 + interviews 810 = 3856.
glance(day)
#> # A tibble: 1 × 9
#>   n_units n_routes  total lower_bound    gap optimal longest_route travel_unit
#>     <int>    <int>  <dbl>       <dbl>  <dbl> <lgl>           <dbl> <chr>      
#> 1      18        6 571.38      246.68 1.3163 FALSE          115.98 min        
#> # ℹ 1 more variable: cost <dbl>
```

With several teams based in several towns, `schedule_fieldwork()` solves
one multi-depot problem: which base serves each unit, how the routes are
drawn, and how many routes to open when the cost model charges a team-day.
Each base may send at most `teams * days` routes. The routes are then
distributed over the teams and the days available, longest first, and the
calendar says who goes where on which day and whether the work fits.


``` r
bases <- tibble(unit = c("depot", "base2"), lat = c(-8.05, -8.30), lon = c(-35.00, -35.30))
sch <- s |>
  travel_matrix(bases = bases, detour = 1.3, speed = 60) |>
  schedule_fieldwork(
    units = s, teams = c(depot = 1, base2 = 1), days = 6,
    max_length = 480, service_time = 120, iterations = 50, cost_model = daily
  )
sch
#> 
#> ── Field schedule ──────────────────────────────────────────────────────────────
#> 18 units, 2 bases, 2 teams, 6 days available: the work fits.
#> "depot": 15 units, 1 team, 5 routes, 5 of 6 days.
#> "base2": 3 units, 1 team, 1 route, 1 of 6 days.
#> Cost (BRL): 3852.
sch$calendar |>
  select(base, team, day, stops, travel, duration) |>
  head()
#> # A tibble: 6 × 6
#>   base  team      day stops  travel duration
#>   <chr> <chr>   <int> <int>   <dbl>    <dbl>
#> 1 base2 base2-1     1     3  97.735   457.73
#> 2 depot depot-1     1     3 115.98    475.98
#> 3 depot depot-1     2     3 113.02    473.02
#> 4 depot depot-1     3     3  99.319   459.32
#> 5 depot depot-1     4     3  80.049   440.05
#> 6 depot depot-1     5     3  58.638   418.64
autoplot(sch)
```

![Figure of the chunk schedule](figures/routing-teams-schedule-1.png)

For a survey over a whole country the schedule is solved region by region:
`schedule_fieldwork(region = )` takes a table of units and bases with their
region, solves each region with its own bases and combines the calendars,
so no travel matrix over the whole country is ever needed.

The distribution of the routes over teams and days follows a simple rule
(longest route first). When the field has constraints of its own, a team
away on some days, a route that must be done by a given team or before
another, or short routes that could share a day, `schedule_calendar()`
solves that distribution exactly as a small integer programme with the
`highs` package, minimising the last working day.


``` r
off <- tibble(team = "depot-1", day = 1, available = FALSE)
cal <- schedule_calendar(sch, availability = off)
cal$summary
#> # A tibble: 2 × 7
#>   base  units teams routes days_needed days_available fits 
#>   <chr> <int> <dbl>  <int>       <int>          <dbl> <lgl>
#> 1 depot    15     1      5           6              6 TRUE 
#> 2 base2     3     1      1           1              6 TRUE
```

## The solver and how good it is

Instances of up to 13 units are solved exactly, by dynamic programming over
subsets (the optimal tour of every subset, then the optimal partition into
feasible routes), and `optimal` is `TRUE`. Larger instances go to a hybrid
genetic search in the spirit of Vidal (2022): feasible and infeasible
subpopulations of giant tours under adaptive penalties on excess load,
duration and stops, order crossover, the optimal split of Prins (2004), and
a local search with granular neighbourhoods made of 2-opt, Or-opt, relocate,
swap, SWAP* and 2-opt* moves, each priced from the route totals in constant
time. `iterations` is the number of offspring; `alpha` the greediness of the
constructions that seed the population.

The `gap` is measured against a lower bound. For a single tour on a
symmetric matrix it is the Held-Karp 1-tree bound, usually within one or two
percent of the optimum, and a branch-and-bound on those 1-trees then tries to
close it within `certify` seconds (one by default): on the TSPLIB instances
below, four of the seven tours are proven optimal within one second and six
within ten, so for a plan that will be used as is, give the certificate a few
seconds and read `optimal`.
With several routes the only cheap bound is loose (half the sum of the
cheapest incoming and outgoing edge at each node), and gaps of 50 to 70
percent are normal for solutions that are in fact within one percent of the
optimum; judge those by the benchmark below rather than by the gap.


``` r
r_quick <- route_fieldwork(m, units = s, depot = "depot", iterations = 10, seed = 2)
r_long <- route_fieldwork(m, units = s, depot = "depot", iterations = 500, seed = 2)
tibble(quick = r_quick$total, long = r_long$total, bound = r_long$lower_bound)
#> # A tibble: 1 × 3
#>    quick   long  bound
#>    <dbl>  <dbl>  <dbl>
#> 1 260.64 260.64 260.64
```

The solver was run on classical benchmark instances with rounded Euclidean
distances, as the libraries define them (script in the `fieldopt-core`
repository, `examples/benchmark.rs`; one core of a laptop):

| Set | Instances | Setting | Optimal | Mean gap | Largest gap | Time |
|-----------------------|---:|---------------|-------------:|-------:|-------:|-----------:|
| TSPLIB (51 to 101 nodes) | 7 | 2000 offspring | 7 of 7 | 0.00% | 0.00% | 0.6 to 1.8 s |
| Augerat A (CVRP, 31 to 79 customers) | 27 | 2000 offspring | 24 of 27 | 0.01% | 0.15% | 0.7 to 4 s |
| Augerat A | 27 | 200 offspring (default) | 14 of 27 | 0.20% | 1.14% | under 0.4 s |
| Augerat A | 27 | 5 s each | 24 of 27 | 0.01% | 0.15% | 5 s |
| Cordeau MDVRP (50 to 360 customers, 2 to 6 depots) | 23 | 2000 offspring | 11 of 23 at or below best known | 0.29% | 1.5% | 1 to 26 s |

Across eight seeds on four of these instances the gap moved by less than one
percentage point (standard deviation below 0.3 points), so one run with the
default seed is representative. The multi-depot instances are what
`schedule_fieldwork()` solves: the base of every route, the routes and how
many to open, with a limit on routes per base.

For field work, with tens of segments per base and daily limits, the
default settings are therefore enough; raise `iterations` to a few thousand,
or give a `time_limit` in seconds, when the instance has hundreds of units
or when a route plan will be used as is.

## The vrpr engine

The `vrpr` package brings the PyVRP solver to R, a production solver with a
much richer local search (SWAP*, adaptive penalties) and support for time
windows, heterogeneous fleets and multiple depots. `engine = "vrpr"` sends
the same problem to it, with the same inputs and outputs, except that the
limit on a route is either `max_stops` or `capacity`, there is no lower
bound, and the `per_route` cost of a cost model enters its objective. On
the Augerat instances the two engines are equivalent: both reach 24 of 27
optima within a few seconds (mean gap 0.01% for the built-in solver, 0.05%
for vrpr), and both solve the multi-depot schedule jointly. Prefer vrpr for
hundreds of units, for time windows or for heterogeneous fleets. For a schedule with several bases, the vrpr engine
optimises the assignment of units to bases jointly with the routes.


``` r
v <- route_fieldwork(
  m,
  units = s, depot = "depot", max_length = 100,
  cost_model = model, engine = "vrpr", time_limit = 1
)
tibble(fieldopt = days$total, vrpr = v$total)
#> # A tibble: 1 × 2
#>   fieldopt   vrpr
#>      <dbl>  <dbl>
#> 1   354.83 354.83
```